construction update – march 2021

Kira continues to progress well. Onsite works are progressing extremely well with most of the concrete structure almost complete. Looking at the construction of the roof prior to Easter.


Externally, the windows are receiving a final check measurement and will be delivered to site shortly. We are also working on completing all the external structural footings and walls.


Internally, we have commenced brickwork and internal plasterboard framing of the first residential level. Additionally, we are well into services rough in in the basements.


Works planned on site for the next quarter of 2021:
• Completion of structure
• Completion of infrastructure main works (sewer, water, stormwater)
• Fit out of apartments to level 2,3,4


Click below link for more info and to view our construction timeline and 360 degree views


https://hyecorp.sites.firstvue.com.au/kira-9c27/fv-timeline/